49 Hampshire Street

Last Update: January 18, 2024

 

 

Construction of the expansion downstairs
And remodeling upstairs for short-term rental.

 
 

Below Photo taken Thursday, August 31, 2023
The foundation being cut out.

Official Completion:  Tuesday, January 9, 2023
TOTAL COST:  $145,546.85
LABOUR $43,352.96 /  MATERIAL $102, 193.90

 

Below Photos Taken Wednesday, Sept 13, 2023
The foundation footing poured on this day.

 
 

Below is the upstairs entrance and kitchen for the short term rental. 
Barrington built the cabinets and Annick painted them.

 

Below: Wednesday, September 27, 2023

 
 

Below: Thursday, September 28, 2023 -- 9 a.m. foundation poured.

 
 

Below: Some of the building material delivered September 27, 28, 29, 2023

 
 

Below: Sunday morning, October 1, 2023, at 7 a.m. to 4 p.m.
All the main blocks erected.

 

The above photo was taken on November 9, 2023

 

Above photos taken Wednesday, December 13, 2023.  This is the view of the great room, dinning room and new kitchen. 
Notice that the floor has concrete on it.  It was done to level the floor properly for tiling.

 

Below photos taken January 9, 2024.  Official completion day.

 

Below: New kitchen

 

Below: Old kitchen

THE OLD AND THE NEW

OLD